How long does a bathroom renovation take?

Most bathrooms take 4–6 weeks on site. Here's what happens in that time, what comes before it, and what makes it run longer.

4 min read

The short answer

Most bathrooms we build take 4–6 weeks on site, from the first day of demolition to the day you can use the room. Design, selections and any permits come before that, and your finish date is set in the contract before demolition starts.

What comes before the build

Most of the waiting happens before the build, and so do most of the time savings. You choose the layout, tiles, tapware, vanity and mirrors at design stage, so nothing on site waits for a decision.

If the job touches the structure or needs a permit, we tell you at the first visit and lodge it ourselves.

What happens on site, in order

  1. 01Demolition

    The noisiest days. Everything comes out back to the frame, and anything hidden behind the old tiles shows up now.

  2. 02Plumbing and electrical

    New pipes, drains and wiring are run to the new layout while the walls are still open.

  3. 03Waterproofing

    The wet areas are sealed and left to cure. It's quiet on site, but nothing can be tiled until it's done.

  4. 04Tiling

    Often the longest stage, especially with tiles floor to ceiling. The floor goes down first, then the walls.

  5. 05Fit-off

    The room starts to look finished: vanity, toilet, tapware, screen, mirrors and lights.

  6. 06Handover

    A final clean, a walkthrough with you, and the room is yours to use.

What makes it take longer

  • Moving plumbing. A toilet or shower in a new spot needs new pipes run through the floor or wall.
  • What's behind the walls. Rot, old pipes or failing drains only show once the room is opened, and fixing them adds days.
  • Made-to-measure pieces. A custom vanity or stone top is made to order, so it's ordered early.
  • More than one room. Two or three bathrooms take longer overall, but one job is usually quicker than the same rooms done one after another.

How long you'll be without a bathroom

Usually the real question. If it's your only bathroom, you'll be without it for most of the build, so work out early where you'll shower for those weeks. If there's a second toilet or shower in the house, ask us at the first visit whether it can stay in use.

Planning a bathroom? Book a free consultation and we'll talk through how long yours would take, and how long you'd be without it.

Enquire

Tell us about your project.

A short form to start. Here's what happens next.

Prefer to call? 1300 909 808

Up to $10,000 of interior design included on new design & construct projects.

Add more detail (optional)

A preference, not a booking.

Helps us understand the project. It isn’t used to set the estimate.

Interest only, not a selection or a quote.

The first phone or video conversation is free. See our privacy policy.

  1. 1

    A free phone or video conversation

    About the project, the location, where you’re up to and your priorities.

  2. 2

    Builder review

    The builder reviews the scope and preliminary estimate before talking it through with you.

  3. 3

    In-depth consult, if you go ahead

    A consult at your home, from $250 + GST, or $350 + GST for full homes and extensions (subject to distance and scope; free in postcode 3012). If you choose Forefront as your builder, a paid fee is credited against your total bill.

  4. 4

    Design, documents and contract

    Before anything is built.